PDA

View Full Version : Alligator Bayou rooms renovated?



pigsinspace
08-28-2011, 01:11 PM
Does anyone know if any of the AB buildings at POR have gotten queen beds yet? If so, which buildings?

Thanks!:mickey:

ibelieveindisneymagic
08-28-2011, 05:26 PM
From what I understand, a couple of the Mansions have re-opened, but the vast majority of the rooms are still to be done in the resort, as the rehab won't finish until mid 2012.

wickedgin
08-28-2011, 07:42 PM
[A Port Orleans site] has a tentative schedule of the refurbishments. Their timeline has 36-39 being refurbished beginning Oct. 25.

pigsinspace
08-28-2011, 08:32 PM
Thanks for the info! I'll check that out.

crltkcagle
08-28-2011, 10:14 PM
Magnolia Bend, Acadian House: starts 26 June 2011, for approx. six weeks
Magnolia Bend, Magnolia Terrace: starts 31 July 2011, for approx. six weeks
Alligator Bayou, Lodges 36, 37, 38, 39: starts 25 October 2011, for approx. eight weeks
Magnolia Bend, Oak Manor: starts 15 January 2012, for approx. five weeks [Royal Themed Rooms]
Magnolia Bend, Parterre Place: starts 19 February 2012, for approx. five weeks [Royal Themed Rooms]
Alligator Bayou, Lodges 24, 16, 17, 28: starts 3 April 2012, for approx. eight weeks
Alligator Bayou, Lodges 14, 27, 18, 15: starts 8 May 2012, for approx. seven weeks
Alligator Bayou, Lodges 25, 35, 26, 34: starts 5 June 2012, for approx. eight weeks